rail construction work
More Light Rail Track Repairs Coming
01/16/2020
Deanna Bolio

Note: This article has been updated to include the construction schedule.

Attention riders, beginning next weekend (Jan 24-26) you may notice occasional shutdowns along parts of the VTA light rail system over the next few months. Weekend bus bridges will provide temporary service during construction as VTA continues making great strides towards assuring our system remains safe, reliable, and moving at its intended speed.

In an effort to rehabilitate our aging infrastructure, VTA is repairing areas on the light rail tracks that have caused our service to run at a slower pace and locations where equipment has reached the end of its useful life. We have identified several locations for repairs and replacements.

Construction Schedule (weather and conditions permitting):

Saturday, January 25 - Sunday, January 26
Construction on San Carlos Street at Market Street
Convention Center station will be closed. A bus bridge will be in effect between Paseo de San Antonio and the Children's Discovery Museum (blue line) and San Fernando (green line) stations.
 

Saturday, February 1 - Sunday, February 2
Construction on San Carlos Street at Almaden Boulevard
Convention Center station will be closed. A bus bridge will be in effect between Paseo de San Antonio and the Children's Discovery Museum (blue line) and San Fernando (green line) stations.
VTA Service Alert

Saturday, February 8 - Sunday, February 9
Construction on San Carlos Street at Woz Way
Convention Center and Children's Discovery Museum stations will be closed. Virginia Station will be closed for northbound trains, but will remain open for southbound trains. A bus bridge will be in effect between Paseo de San Antonio and the Tamien (blue line) and San Fernando (green line) stations. 

Be sure to check the schedule when planning your trip. Subscribe for updates at: www.vta.org/subscribe

 