Notice Cause
Construction
Notice Effect(s)
Noise
Parking Lot Closure
Start Date
End Date
What
- Contractors will be conducting subsurface explorations around the future Diridon Station to help prepare for VTA’s BART Silicon Valley Phase II Project.
Where
- The work will take place in the parking lot in front of the SAP Center, along Santa Clara St, and between Cahill St. and Montgomery St.
When
- Work is planned for Mon. June 3 – Fri. June 7.
- General working hours will be 7:00AM-5:00 PM.
* Please note that timelines for construction activity have some inherent uncertainty and may change depending on field conditions and/or inclement weather.
What to Expect
- The work activity will be completed with a truck-mounted, mud rotary drill rig and support water truck.
- There will be periodic, repetitive hammering during soil sampling.
- The work does not typically generate dust.
- The work area will be delineated by barricades and caution tape. About 10 to 15 parking spots may be blocked.
Why
- Necessary to help prepare for VTA’s BART Silicon Valley Phase II Project.
Community Impacts
- None