Notice Cause
Construction
Start Date
End Date
What
Full freeway closure between 5/3-5/10 nightly, for the removal of falsework (temporary support structure for the bridge) of the US 101/Blossom Hill Road overcrossing. Changeable message signs and directional signs will be in place to assist motorists traveling in the area. The schedule is subject to change based on weather and other conditions.
Southbound US 101 freeway closure beginning 5/3/21, between 12:00 AM to 5:00 AM.
- Closure of southbound (SB) lanes will start at Hellyer Ave. until all lanes are closed approaching Blossom Hill Rd., except the off-ramp.
- Detour - SB 101 traffic will exit at Blossom Hill Rd off-ramp, turn left at Blossom Hill and then turn right onto SB 101 on-ramp.
Northbound US 101 freeway closure beginning 5/5/21, between 12:00 AM to 4:00 AM.
- Closure of northbound (NB) lanes will start at Bernal Rd. until all lanes are closed approaching Blossom Hill Rd., except the off-ramp.
- Detour - NB 101 traffic will exit at Blossom Hill Rd off-ramp, turn left at Blossom Hill and then turn right onto NB 101 on-ramp.