Notice Cause
Construction
Notice Effect(s)
Detour
Lane Closure
Noise
Noise and Vibration
Traffic Delays
Start Date
End Date
What
Why
Project contractors will be performing grading, paving, and striping to shift traffic to the new north half of De La Cruz Boulevard Overcrossing.
Detour
DETOUR: From Southbound De La Cruz Blvd. to Southbound US-101
- RIGHT on CENTRAL Expy
- RIGHT SCOTT Blvd
- RIGHT SAN TOMAS Expy
- ENTER Southbound US-101 (END OF DETOUR)
DETOUR: From Southbound US-101 to De La Cruz Blvd
- Exit FIRST St
- Left on FIRST St
- Enter Northbound US-101
- Exit DE LA CRUZ Blvd/ TRIMBLE Rd (END OF DETOUR)
Community Impacts
For the safety of the public and construction workers, traffic control measures will be used when needed. Information and warning signs will be posted to ensure safety. Construction crews will make every effort to minimize inconvenience to motorists, bicyclists, pedestrians, businesses, and neighbors.
Traffic Impacts
Temporary and new traffic signals will be activated to open the on and off ramps to the new alignment starting 2/6/22.
Once traffic is shifted to the new permanent portion of the overcrossing, demolition of the old overcrossing will begin.